Update on Oakwood Road footpath

s we had not received a response from SCC it was chased today and a response received confirming that drainage improvement works to the culvert and the surface water drains will start on the 17th October for a duration of 3-4 days. The work will involve the drainage system followed by pipe lining the known defects to prevent future leaks.

The outlined design for the retaining wall was only received last week and is currently being reviewed  by the SCC Engineers and potential contractors. The next stage will be to update the design and drawings and issue the scheme for pricing. SCC are currently targeting March as a potential start date. SC C have said they will try and keep us updated.