Windlesham Field of Remembrance New Pavilion Update

Windlesham Field of Remembrance

New Pavilion Update

 

Work has already started on the demolition of the old building, as a specialist contractor has now been in and removed the asbestos. 

A hoarding will be going up around the building during next week, and the demolition of the building has now been programmed to start on Monday 6th August.  We are delaying the start of the demolition so that there will be accessible power and water for the Royal British Legion Centenary event on Saturday 4th August. 

There will be some disruption whilst the demolition is carried out but access to the field will be maintained and the demolition area will be protected with a hoarding. 

We are anticipating hearing about our grant applications within the next few days and we will issue a further update when we can, so please keep your fingers crossed!